Design + Development project checklist

End to end - design it, build it, test it, launch it. 161 items across 8 stages, 33 of them needed from the client.

For: The whole delivery team

01Before we start

  • Signed proposal or contractKeyFrom client

    Countersigned, not "verbally agreed". Work started on a promise is work that may not be paid for.
  • Deposit or first invoice paidKeyFrom client

    The payment condition in the contract, met. This is the line the sales SOP will not let a project pass.
  • Decision-maker confirmed by nameKeyFrom client

    Who signs things off, and who can say no. A project approved by a committee is a project approved by nobody.
  • Day-to-day contact named, and their working hoursFrom client

    Including timezone. Half of "they are slow to respond" is a five-hour offset nobody wrote down.
  • Billing contact and PO or reference number, if they need oneFrom client

    Ask now. An invoice rejected in month three for a missing PO number delays payment by a month.
  • Sales-to-delivery handoff completedKeySales

    Call notes, proposal versions, commitments, risks and stakeholders - everything promised during the sale, in writing, where delivery can read it.
  • Scope, exclusions and assumptions restated in our own wordsPM

    Written by the people delivering it, not copied from the proposal. Rewriting it is how you find what the proposal left ambiguous.
  • Project workspace, folders and client portal set upPM

    Client invited and confirmed able to sign in - not "invitation sent".
  • Team assigned with named owners per disciplinePM

    One name per discipline. "The design team" is not an owner.
  • Commercials checked against capacity before any date is promisedPM

    The PM SOP puts this before assignment on purpose: a timeline agreed without checking the calendar is a timeline that will be missed.
  • NDA or data-handling requirements identifiedPM

    If they handle health, financial or children’s data, that changes where things may be stored - and it is cheaper to know now.

02Kick-off

  • Review turnaround agreed in working daysKeyFrom client

    How long feedback takes. Every date in the plan is built on this number, so it is agreed rather than assumed.
  • Feedback consolidated through one personFrom client

    Contradictory feedback from three stakeholders is the single most common cause of rework.
  • Client team introduced, including anyone who can vetoFrom client

    The person who appears in week eight to reject everything was always going to appear. Better in week one.
  • Holidays, launches and blackout dates on both sidesFrom client

    Their trade show and our public holidays, on the plan before it is signed off.
  • Kick-off call held with the decision-maker presentKeyPM

    Whole delivery team plus whoever signs off. A kick-off without the decision-maker has to be repeated.
  • Milestones and delivery dates agreed in writingKeyPM

    With internal review dates set before each client-facing date, never on the same day.
  • Kick-off notes circulated with decisions, owners and next actionsPM

    Within 24 hours, while people still agree on what was said.
  • Communication channel and update cadence agreedPM

    Where we talk, how often we report, and what counts as urgent. Written down, so "I messaged you on WhatsApp" is not a delivery method.
  • Escalation path agreed both waysPM

    Who to call when something is going wrong, on their side and on ours, before it is going wrong.
  • Change-request process explained and acceptedPM

    How a new request gets costed and scheduled. Explaining it at the kick-off is a conversation; explaining it in week seven is a confrontation.
  • Risks and dependencies logged with ownersPM

    The PM SOP asks for risks raised early with a proposed solution, not only the problem.
  • QA present at the internal kick-offQA

    QA that joins after the build has already missed the requirements it is meant to test against.

03Discovery

  • Brand assetsKeyFrom client

    Logo in vector, fonts with their licences, colour values, existing guidelines. "We will send the logo" usually means a PNG off the website.
  • Copy supplied, or a decision that we write itKeyFrom client

    The single most common cause of a stalled design project. Designing around copy that has not been written means designing twice.
  • Domain registrar access, or a named person who can change DNSKeyFrom client

    Find this out in week one. Discovering on launch day that nobody knows the registrar password is a launch that slips.
  • Acceptance criteria agreedKeyFrom client

    What "done" means, written before testing rather than argued after it.
  • Business goal for this project, in a numberFrom client

    More leads, fewer support tickets, faster checkout. Without a number, "did it work" is a matter of opinion.
  • Who the audience is, and what we want them to doFrom client

  • Competitors you actually lose toFrom client

    Not the biggest names in the category - the ones that come up in your deals.
  • What must not changeFrom client

    The thing their customers recognise, or the integration that cannot break. Cheaper to hear now than to rebuild later.
  • Examples of work you like - and work you do notFrom client

    Three of each is plenty. The dislikes are more useful than the likes, and faster to act on.
  • Photography and video supplied, or approval to licence stockFrom client

  • Sitemap or screen list signed offFrom client

    The thing that turns "a website" into a countable amount of work.
  • Hosting account, or a decision that we provide itFrom client

  • Third-party accounts and API keysFrom client

    Analytics, email, CRM, payments, chat - whatever the build touches. Sent through the vault, never in a chat message.
  • Existing site and CMS access, if we are replacing somethingFrom client

    So content can be migrated rather than retyped, and so old URLs can be redirected rather than lost.
  • Content ready, or a signed-off placeholder planFrom client

  • Legal pages supplied or approvedFrom client

    Privacy, terms, cookies. Their lawyer’s wording, not ours - we are not the ones who carry it.
  • Test accounts, sample data and any sandbox credentialsFrom client

  • Devices and browsers that matter to their usersFrom client

    Their real analytics beats our assumptions, and usually shortens the matrix.
  • Requirements written down and confirmed back to the clientKeyPM

    In their words and ours. The confirmation is the point: it is where a misunderstanding surfaces while it is still free.
  • Accessibility target set before design startsKeyDesign

    WCAG 2.2 AA is the default expectation for commercial work now. Contrast and text sizing are cheap to design in and expensive to retrofit.
  • Browser and device support agreed and written downKeyDev

    Including what is out of scope, so a request in week eight has an answer that is not an argument.
  • Test plan written: scope, environments, device matrix, risk areasKeyQA

    Plus the severity classification - critical, high, medium, low - agreed before the first bug is raised, so severity is a fact rather than a negotiation.
  • Existing material reviewed before asking for morePM

    Their analytics, support tickets and sales objections are research that is already written down and already paid for.
  • Dependencies mapped between content, design, build and approvalsPM

    Which piece cannot start until which other piece finishes, and who is holding each one.
  • Missing information listed and requested as one batchPM

    One clear request beats eleven emails over three weeks, and gives the client something they can actually work through.
  • Task breakdown created with owners, reviewers and internal deadlinesPM

  • Design review rounds agreed, and what happens after themDesign

    How many are included, and what an extra round costs. Agreed now, not during round four.
  • Performance budget setDev

    A target before anything is built: LCP under 2.5s, INP under 200ms, CLS under 0.1 on the pages that matter.
  • Technical approach agreed and the reasons recordedDev

    Stack, CMS, integrations. Written down because in a year the reasons are what make the next change cheap.
  • Test cases written: module, scenario, steps, expected result, priorityQA

    The tracker format from the QA SOP. Test cases written after testing are a description, not a plan.

04Build

  • Staging environment live and shared with the clientKeyDev

    Password-protected and excluded from search engines. A staging site that gets indexed competes with the real one.
  • Environment variables and secrets stored in the vaultKeyDev

    Not in the repository, not in a chat message, not in a spreadsheet called passwords.
  • Backups running, and a restore actually testedKeyDev

    A backup nobody has restored from is a belief, not a backup.
  • Art direction or moodboard shared and agreedDesign

    Agreeing direction before pixels is what stops round two being a restart.
  • Wireframes for the key templatesDesign

    Structure agreed while it is still cheap to move.
  • Design system started: type scale, spacing, colour and componentsDesign

    Built as styles and variables, not hand-typed values - which is how a design system quietly stops being one.
  • Every screen designed at mobile as well as desktopDesign

    Designed, not "it will reflow". Reflowing is a decision somebody makes; if it is not the designer, it is the developer, at 6pm.
  • Interaction states designed: hover, focus, active, disabled, loadingDesign

    Focus especially. It is the state that keyboard users live in and the one that is skipped most.
  • Empty, error and success states designedDesign

    The three states every design skips and every user eventually meets.
  • Forms designed with labels, validation, error wording and long-value behaviourDesign

    Including what a field looks like with a 60-character value in it.
  • Content extremes testedDesign

    The longest product name, the shortest bio, eleven nav items. Designs break at the edges, never in the middle.
  • Repository created, access granted, branching agreedDev

  • Built from the design system rather than from screenshotsDev

    Tokens and components, so a colour change is one change.
  • Responsive behaviour implemented at the agreed breakpointsDev

    375, 768, 1024 and 1440 as the baseline, plus whatever their analytics actually shows.
  • Forms wired end to end, including where a submission lands and who is toldDev

    A form that validates beautifully and emails nobody is the most common launch bug there is.
  • Content editable by the client where it was promised to beDev

    If they were told they could change it themselves, check that they can, on their own login.
  • Error and empty states built, not just the happy pathDev

  • Analytics and error reporting installed and firingDev

  • Rollback plan written for launch dayDev

    What we do if it goes wrong, decided while nobody is panicking.
  • Redirect map built from the old URLs, if replacing a siteDev

    Every indexed URL either resolves or redirects. This is where migrations lose traffic.
  • Environment readiness confirmedQA

    Staging opens on every device, logins work, permissions are right, and test payments and dummy data are enabled.

05Internal review

  • Internal review complete before anything reaches the clientKeyPM

    The PM SOP is blunt about this: no drafts, no unreviewed work, no outdated versions sent to a client.
  • Developer handover walkthrough heldKeyDesign

    Walk the build team through the deliverables, show where assets live, and answer questions in the room rather than over three days of messages.
  • Admin routes and private data confirmed protectedKeyDev

    Log out and try to reach them. Security by nobody-knowing-the-URL is not security.
  • Responsive pass at 375, 768, 1024 and 1440KeyQA

    No overflow, menus behave, tap targets at least 48px, forms scroll and submit.
  • Browser pass on at least three: Chrome, Safari, and Firefox or EdgeKeyQA

    Safari on real iOS, not an emulator - it is where the differences actually live.
  • Regression pass after fixesKeyQA

    Re-test every resolved issue and re-walk the key flows. Fixes break things; that is what regression testing is for.
  • Reviewed against the scope, not just against "does it work"PM

    Every requested item, every feedback point, every agreed state present.
  • No placeholders, lorem ipsum, or test content left anywherePM

  • Version and file naming correct, and the client is getting the right onePM

    Sending v3 when v4 exists costs a review cycle and some credibility.
  • Colour contrast measured, not eyeballedDesign

    4.5:1 for body text, 3:1 for large text and interface elements.
  • Spacing, alignment and type scale consistent across every screenDesign

    The QA SOP calls this out for a reason: it is what separates finished work from nearly finished work.
  • Only design-system styles used - no manually entered colours or one-off sizesDesign

    A hand-typed hex is how a design system starts drifting, one screen at a time.
  • File organised and named for someone who did not build itDesign

    Pages, layers and components named. Handing over a file only its author can navigate is not handing it over.
  • Design decisions annotated where the reason is not visibleDesign

    The annotation answers the developer question you would otherwise answer in a call.
  • Code reviewed by someone who did not write itDev

  • No console errors on any page, including during interactionsDev

  • Images optimised and served in a modern formatDev

    Nothing over 100KB without a reason, and nothing scaled down in the browser.
  • Unused libraries, dead code and commented-out blocks removedDev

  • No references to staging, test accounts or local URLs anywhereDev

    Including in image paths, canonical tags and structured data.
  • Functional pass: navigation, buttons, forms, links, sliders, popupsQA

    Every module, against the test cases, not by wandering around the site.
  • Login, logout and session behaviour testedQA

    Including what happens when a session expires mid-form.
  • Cart and checkout tested end to end, where applicableQA

  • Role-based access tested from each role, including logged outQA

    The test that finds the data leak. Try to reach the thing you should not be able to reach.
  • Visual QA against the design fileQA

    Font sizes and weights, radius, padding, margins, icon placement, white space, alignment.
  • At least one test on a real physical deviceQA

    Emulators do not reproduce touch, keyboards, or a slow connection on a train.
  • Accessibility pass: contrast, alt text, focus order, labels, ARIAQA

    WCAG 2.2 AA, checked with a tool and with the keyboard. Tab through the whole thing without touching the mouse.
  • Performance measured against the budgetQA

    Lighthouse above 80 on mobile and 90 on desktop, Core Web Vitals within thresholds, network tab checked for oversized payloads.
  • SEO and metadata verifiedQA

    Unique titles and descriptions, one H1 per page, Open Graph tags, favicon, alt text, sitemap and robots.
  • Broken links, redirect chains and the 404 page checkedQA

  • Forms, payments and integrations tested end to end with real submissionsQA

    Follow the data to where it lands. A form is not tested until someone has received one.
  • Every bug logged with evidenceQA

    Screenshot or recording, OS and browser, severity, steps to reproduce, and an assigned developer. A bug report without steps is a conversation.
  • Reopened bugs tracked rather than quietly re-closedQA

06Client review and sign-off

  • Written sign-off recordedKeyFrom client

    In the portal or in writing. Per the MSA a portal approval is binding, which is exactly why it is worth having.
  • Feedback collected in one placeFrom client

    One thread, one document. Feedback spread across email, calls and messages is feedback that will be missed.
  • QA sign-off given, with known issues stated honestlyKeyQA

    Total cases, bugs by severity, what is deferred, and device coverage. Sign-off with a hidden known issue is not sign-off.
  • Walkthrough delivered rather than a link dropped in a chatPM

    Ten minutes of context turns "I do not like it" into specific, actionable feedback.
  • Every feedback point converted into a tracked item and closedPM

    Tracked by version, so "we told you about that" has an answer either way.
  • Anything out of scope identified, costed and agreed - not absorbed silentlyPM

    Quietly absorbing scope teaches a client that scope is free, and the next request will be bigger.
  • Deferred low-priority bugs listed and accepted, not forgottenQA

    Written down and agreed, so they are a decision rather than a discovery.

07Launch

  • Post-go-live smoke test on the live domainKeyQA

    Forms, popups, carts, logins, CTAs - on production, on mobile and desktop. Staging passing is not production passing.
  • Launch date and window agreed, and who is available during itKeyPM

    Not a Friday afternoon. Not the day before a holiday. Somebody on call for the hours after.
  • Pre-launch backup of everything being replacedKeyDev

    Files and database, taken and verified before the switch, not after.
  • DNS and domain pointing confirmed, including www and the apexKeyDev

    Both hosts resolve, and one redirects to the other. Sessions and SEO both depend on picking one.
  • HTTPS valid across every URL, with no mixed contentKeyDev

  • Search engine blocking removed from productionKeyDev

    The staging robots rule that follows a site to production is the classic launch mistake - and it is invisible until traffic never arrives.
  • Analytics, GA4 and any pixels confirmed firing on productionQA

    Real-time events on the real domain, before any paid traffic is pointed at it.
  • Lighthouse re-run on the live siteQA

    Production is where the CDN, the real images and the third-party scripts finally all show up together.
  • Redirects live and spot-checked against the old URL listDev

  • Sitemap submitted and the property verified in Search ConsoleDev

  • Transactional email tested from productionDev

    Enquiry, receipt, password reset. Check it arrives and does not land in spam - which is a different question from whether it sends.
  • Monitoring and uptime alerts pointed at the live domainDev

  • Client told it is live, and what to watch for in the first 48 hoursPM

  • First-week check-in booked before leaving launch dayPM

    Launch is a window, not a button. Most of what a launch breaks shows up in the following week.

08Handover and close

  • Someone named as the owner on their sideKeyFrom client

    A handover to a company is a handover to nobody. It needs a person with a name.
  • Final sign-off recordedKeyFrom client

  • Access confirmed working from their sideFrom client

    Tested with them on the call - not "we have sent the details".
  • Testimonial or case-study permission, in writing, if they are happyFrom client

    Ask at the moment they are happiest. Written permission, because the sales SOP does not allow publishing client work without it.
  • All credentials transferred to the client’s own accountsKeyDev

    Nothing important should remain only in our name. This is the item that decides whether they are a client or a captive.
  • Domain, hosting and DNS ownership confirmed as theirsKeyDev

  • Billing for any service in our name transferred or cancelledKeyPM

    Hosting, plugins, licences, mail. So nothing stops working the day our card expires.
  • Outstanding items and known issues written down honestlyKeyPM

    Everything unfinished, deferred or broken. A handover that hides a known issue is found out, and it is found out by the client.
  • Repository access transferred or grantedDev

  • Analytics, Search Console and ad account ownership moved to the clientMarketing

  • Our access removed or reduced, and the client told what we keptPM

    If we keep a login for support, say so in writing rather than leaving it quietly in place.
  • Documentation written for whoever maintains it nextPM

    Written for a person who was not here, which is the only audience that matters.
  • Training session delivered and recordedPM

    The recording is the deliverable. The person trained will leave.
  • Final files, source files and meeting records stored in the client folderPM

  • Final invoice raisedPM

  • Project archived here, with files and notes kept in the vaultPM

    Archived, never purged - the knowledge is what makes the next project with them cheap.
  • Internal retrospective: what to do differently next timePM

    Fifteen minutes. The PM SOP asks for one practical process improvement, not a document.
  • Final designs for every agreed screen, desktop and mobileDeliverableDesign

  • Source files handed over, organised and namedDeliverableDesign

    Figma access or the working files. Access that expires is not a handover.
  • Component library or design system documentedDeliverableDesign

  • Assets exported in the formats needed, at the densities neededDeliverableDesign

  • Brand or usage guidelines, where in scopeDeliverableDesign

  • Working site or application on productionDeliverableDev

  • Source code in a repository the client owns or can accessDeliverableDev

  • Deployment and environment documentationDeliverableDev

    How to build it, where it runs, what it depends on, and how to put a change live.
  • Admin or CMS access, with a walkthroughDeliverableDev

  • Warranty or support period stated in writingDeliverablePM

    What is covered, for how long, and what counts as new work.
  • QA summary reportDeliverableQA

    Cases run, bugs found and their status, deferred items, device and browser coverage, sign-off note.
  • Final test case sheet with resultsDeliverableQA

  • Bug log archived with evidence attachedDeliverableQA

    Kept for the support window, so a question in month two has a record behind it.
  • Handover pack with every credential and where it livesDeliverablePM

  • Maintenance or support arrangement agreed, or explicitly declinedDeliverablePM

    Explicitly declined is a real outcome, and better than an assumption on either side.
  • Recording and notes from the training sessionDeliverablePM

  • Written summary of what was built and what was decidedDeliverablePM

    The reasons, not just the result. It is what makes the next change cheap.